EDIT - Benefit Maximums

There are 5 different Benefit Maximum edits available in the system. All the benefit maximums are accumulated at the member level.  There are no maximums established at the Family level.

Benefit Maximum Type Description 
Plan Pay Max Accumulation
  • Plan Pay accumulation maximums are used when the benefit for a drug/group of drugs is limited.  An example is a $300.00 limit per year for Fertility medications. 
  • This is NOT Plan Stop Loss accumulation.
Quantity Max Accumulation Quantity Max accumulation edits are used to accumulate the quantity dispensed to a set maximum.  For instance, a member may be allowed a quantity of 7 tablets of migraine medication every 30 days.
Units Max Accumulation
  • Accumulates total units. Submitted Quantity divided by the package size.  For instance, inhaler is 7.2gm for 1 pkg as well as 14.4gm for 1 pkg.  Max Units for an edit maybe 5.  In this case, 5 inhalers without regard to package size.
  • This rule is ignored for multi-ingredient compounds drug.  
Fills Max Accumulation This edit accumulates the number of Rx Fills to a maximum.  An example of this, Opioids have a benefit maximum of 1 fill every 7 days.
Day Supply Max Accumulation

This edit Accumulates the total maximum days supply. For eg., Plan will cover 180 days of smoking cessation medications.  Smoking cessation medications would be defined in the Criteria. 


Plan Pay Max Accumulation

Quantity Max Accumulation

Units Max Accumulation

Fills Max Accumulation

Days Supply Max Accumulation

Fields

Almost all the fields are the same in all max accumulation edits. 

  • Benefit Amount is the field where the appropriate value should be provided based on the Max Accumulation type. 
  • Drug Level is applicable only for Fills max. This is the Drug Hierarchy level to which the accumulation maximum refers.  From NDC11 to ALL (by GPI, ie., GPI14, GPI12, …GPI2, All)



Benefit Maximums Plan Pay Quantity Max Units Max Fills Max Day Supply Max
Claim Type All, POS, DMR All, POS, DMR All, POS, DMR All, POS, DMR All, POS, DMR

Network

Classification

All, In Network, Out of Network All, In Network, Out of Network All, In Network, Out of Network All, In Network, Out of Network All, In Network, Out of Network
Network Type All, Retail, Retail 90, Mail, Specialty, Other All, Retail, Retail 90, Mail, Specialty, Other All, Retail, Retail 90, Mail, Specialty, Other All, Retail, Retail 90, Mail, Specialty, Other All, Retail, Retail 90, Mail, Specialty, Other
Period Type Lifetime, Term, Rolling, Every X Days Lifetime, Term, Rolling, Every X Days Lifetime, Term, Rolling, Every X Days Lifetime, Term, Rolling, Every X Days Lifetime, Term, Rolling, Every X Days
Start Date Term & Lifetime Only Term & Lifetime Only Term & Lifetime Only Term & Lifetime Only Term & Lifetime Only
Duration, Period Day, Month Day, Month Day, Month Day, Month Day, Month
Duration Length Duration Period Duration Period Duration Period Duration Period Duration Period
Benefit Amount Max. Plan Pay Amount Maximum Quantity Maximum Units Maximum # of fill Maximum Days supply
Drug Level Not Applicable Not Applicable Not Applicable All, NDC 11, NDC 9, GPI 2 - GPI 14 Not Applicable
Age, Min No decimals allowed No decimals allowed No decimals allowed No decimals allowed No decimals allowed
Age, Max Less than 151, No decimals allowed. Less than 151, No decimals allowed. Less than 151, No decimals allowed. Less than 151, No decimals allowed. Less than 151, No decimals allowed.
Refill Margin, TYPE (for every X days only) Days, Percent Days, Percent Days, Percent Days, Percent Days, Percent
Refill Margin, % or # Days % or Days % or Days % or Days % or Days % or Days
DMR Processing

Process as Submitted

Reduce to maximum

Process as Submitted

Reduce to maximum

Process as Submitted

Reduce to maximum

Process as Submitted

Reduce to maximum

Process as Submitted

Reduce to maximum

Maximums Limitation

Apply to all Maximums

Apply Maximums Then Ignore

Ignore all Accumulation Maximums

Apply to all Maximums

Apply Maximums Then Ignore

Ignore all Accumulation Maximums

Apply to all Maximums

Apply Maximums Then Ignore

Ignore all Accumulation Maximums

Apply to all Maximums

Apply Maximums Then Ignore

Ignore all Accumulation Maximums

Apply to all Maximums

Apply Maximums Then Ignore

Ignore all Accumulation Maximums

Reject Message

Prior Auth Required

Limits Exceeded

Prior Auth Required

Limits Exceeded

Prior Auth Required

Limits Exceeded

Prior Auth Required

Limits Exceeded

Prior Auth Required

Limits Exceeded

Compounds Bypass, Process Bypass, Process Bypass, Process Bypass, Process Bypass, Process



Period Types


Period Type Comments
Lifetime This type of period has a beginning date and no end date associated with it.
Term The Term period has a defined start date and then a defined number of days or months.
Rolling This type of period accumulates for a fixed period (days or months) and then restarts for another fixed period of the same length.  As an example, a Day Supply Accumulation may be every 3 months.  The maximum accumulation period begins on the Date of Service of the first claim for the member that meets the criteria for the EDIT.
Every X Days This type of period resets accumulations every X days.  This period type requires a look back in history of X days from the claim date of service, X days after the claim date of service, AND X days divided by 2 before and after the date of service. The maximum accumulation period begins on the Date of Service of the first claim for the member that meets the criteria for the EDIT.


Reject Message

The selected reject message will be used if the claim exceeds the benefit maximum


Options Reject Message in Response Description
Prior Authorization Required 75 - Prior Authorization Required

If this option is selected, the claim will be rejected with reject code 75. There is no option to override this rejection.

Member should have a PA in order to process the claim

Limits Exceeded 76 - Plan Limitations Exceeded

If this option is selected, the claim will be rejected with reject code 76. You can allow override by selecting the option


Maximums Limitation

Type Description
Apply to all Maximums If the EDIT is established with this Maximum Limitation type, the accumulation maximum will be calculated and applied
Apply Maximum Then Ignore If this Maximum Limitation is selected, the accumulation maximum for this edit will be used but any lower-level accumulation limitation will be ignored.
Ignore all Accumulation Maximums If this Maximum Limitation is selected, the accumulation maximum for this edit will be ignored and all ensuing accumulation maximum edits will be ignored.
Ignore All Maximums for this Edit type

MEMBER LEVEL ONLY.  This means that this EDIT will not be accumulated to any other accumulation of this type.

The reason for this option is to allow more than one MAXIMUM EDIT to apply to a claim.  This may be needed if an NDC is part of different Maximum EDITs criteria.  For instance, Criteria A has a quantity maximum and Criteria D has a quantity maximum.  The NDC is reflected in both Criteria.

This option is Not available

Refill Margin

This is effectively a more specific refill too soon edits for the accumulator.  Specifies how early from the end of the prior fill can the prescription be refilled.  For instance, a claim on 3/1/2018 with a 30-day supply.  The EDIT is Every 30 Days.  Without a tolerance, a member would have to use all the prescription before being able to have a refill processed successfully.  The Refill Margin provides the ability to refill the Rx before the member runs out.  In the example above, if the DAYS was 6, the member could have a refill processed 6 days before the end of the Full Day Supply.  If the EDIT has a Percentage set at 70, 70% of the initial prescription (70% x 30 days = 21 days) must be “used” before a refill can be processed.

    • Days:  a value of ZERO is valid and indicates a DAILY maximum.  (allow only full days)
    • Percent:  the % of the previous fill to be used before a refill can be processed.  (allow 2 decimal points)

DMR Processing

    • Process claim as submitted
    • Reduce submitted values
      • Plan Dollar, Day Supply or Quantity are reduced to the EDIT maximum For instance, if the Quantity accumulation total is 100 and it is currently at 95, only 5 Quantity are left for coverage.  The process should reduce for this limitation the submitted quantity to 5, price and process the claim.